Project Milestone - FMG Berth 4, Anderson Point

The FMG Berth 4 Anderson Point project has successfully off loaded all modules from the last of the three Heavy Lift Vessels (HLVs) scheduled for the project. The completion of the transportation by the HLVs of all the modules allows the team to get stuck in and finish off the wharf.

The first HLV arrived on the 10th October followed by the second on 8th November 2012. All in all, 10 wharf modules, one modularised transfer station, and 43 conveyor modules and associated steel work were transported via the three HLVs.