The Company is pleased to advise that final inspection of the waterway at Bogong Hydro Electric Scheme was successfully completed on the 4th September and the tunnel plug door closed.
Filling of the main headrace tunnel commenced at 14:00 AEST via the cooling water offtake at McKay Creek (around 200L/s) to provide a buffer of water up against the plug prior to the main fill commencing.
Water will be directed into the waterway from the McKay Creek Power Station turbines, from around 06:00 this Sunday, the 6th September. Filling will be controlled such that 20 m head will be added per hour. All going well, the waterway will be filled completely by Monday morning.
This significant milestone has been reached ahead of schedule allowing client AGL to meet their 15 September schedule first rotation of the 70MW Unit 1 turbine.
ENDS
About McConnell Dowell Corporation Limited:
Formed in 1960, McConnell Dowell is a world-class engineering, construction, building and maintenance group employing 7,000 people throughout Australia, Asia, New Zealand, the Pacific and the Middle East. For almost 50 years we have continually delivered the right engineering solutions for our public and private sector clients throughout our operating geographies.
McConnell Dowell’s diverse service offering includes building, electrical, marine, mechanical, pipeline, tunnelling and underground infrastructure capabilities in the key market sectors of commercial building, mining, oil and gas, petrochemical, power, public infrastructure, transport and water.
ENQUIRIES:
Angeleen Jenkins
Director New Business
McConnell Dowell Corporation Limited
P: +61 3 9816 2400
F: +61 3 9819 4856
E:
This e-mail address is being protected from spambots. You need JavaScript enabled to view it
www.mcconnelldowell.com